Model Answer Reasons Behind Untapped Wind Energy Potential in India India has a significant wind energy potential, with estimates suggesting up to 302 GW at a hub height of 100 meters, and 174 GW from offshore resources. However, this potential remains largely untapped due to several factors: ImpactRead more
Model Answer
Reasons Behind Untapped Wind Energy Potential in India
India has a significant wind energy potential, with estimates suggesting up to 302 GW at a hub height of 100 meters, and 174 GW from offshore resources. However, this potential remains largely untapped due to several factors:
- Impact of the COVID-19 Pandemic: The pandemic caused delays in project timelines, along with disruptions in supply chains, which slowed wind energy installations.
- Source: National Institute of Wind Energy (NIWE) and industry reports.
- Concentration of Resources: The high wind potential is largely concentrated in specific regions, primarily Gujarat and Tamil Nadu, leading to inflated land prices that make projects more expensive.
- Cost Gap Between Wind and Solar: The falling cost of solar power has created a wider price disparity between wind and solar, resulting in delayed power supply agreements for wind projects.
- Land Acquisition Delays: Wind projects require large tracts of land, often facing resistance from local communities, further delaying progress.
- Offshore Wind Financing: Offshore wind projects are significantly more expensive, making them harder to finance compared to onshore projects.
- Source: Standing Committee on Energy report.
Suggested Solutions
- Enhanced Coordination: Strengthen collaboration between central and state governments to streamline project approvals, grid balancing, and land acquisition processes.
- Technological Innovation: Develop technology exchange programs and improve the alignment of domestic manufacturing with global supply chains to reduce costs.
- Overcoming Legacy Challenges: Address issues like DISCOM payments, grid infrastructure, and inconsistent state land policies.
- Offshore Wind Development: Implement the 37 GW offshore wind target, focusing on regions like Gujarat and Tamil Nadu, with dedicated roadmaps for growth.
By tackling these challenges, India can unlock its vast wind energy potential and play a crucial role in its transition to a low-carbon economy.
See less
मॉडल उत्तर भारत में पवन ऊर्जा की क्षमता का उपयोग न करने के कारण भारत में पवन ऊर्जा की उच्च क्षमता होने के बावजूद, इसे पूरी तरह से दोहन नहीं किया जा सका है। इसके कुछ प्रमुख कारण हैं: कोविड-19 महामारी का प्रभाव: महामारी के दौरान आपूर्ति श्रृंखला में विघ्न और परियोजनाओं में देरी के कारण पवन ऊर्जा क्षमतRead more
मॉडल उत्तर
भारत में पवन ऊर्जा की क्षमता का उपयोग न करने के कारण
भारत में पवन ऊर्जा की उच्च क्षमता होने के बावजूद, इसे पूरी तरह से दोहन नहीं किया जा सका है। इसके कुछ प्रमुख कारण हैं:
संधारणीय विकास के उपाय
भारत को 2030 तक 50% गैर-जीवाश्म ऊर्जा प्राप्त करने के अपने लक्ष्य को पूरा करने के लिए पवन ऊर्जा में निवेश को बढ़ावा देना होगा।
See lessस्रोत: राष्ट्रीय पवन ऊर्जा संस्थान (2023), ऊर्जा स्थायी समिति (2020)