What is the model of Swiss Challenge? Talk about the benefits and drawbacks of this model. (Answer in 200 words)
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
The Swiss challenge model means a method of public procurement in which an unsolicited proposal is received by a public authority for a project that predominantly involves uniqueness and specificity of design, technology and intellectual property rights. The government then examines the proposal and if the proposal belongs to the declared policy of priorities, then it may invite competing counter proposals from third parties. In the event of a better proposal being received, the original proponent is given the opportunity to modify the original proposal. Finally, the proponent with the best plan is awarded the contract.
In a 2009 ruling, the Supreme Court had approved the Swiss Challenge method for award of contracts. Further, respective state governments were encouraged to draft guidelines for procurement using the Swiss Challenge method. For example, Maharashtra and Karnataka have adopted their own policy guidelines.
Advantages of Swiss Challenge Model
Problems associated with Swiss Challenge Model
However, these issues can be addressed by instituting a national policy framework for the Swiss Challenge method. There should be wider participation and greater flexibility to promote innovation at the pre-proposal stage and sufficient time for counter-bidders to respond at the post-proposal stage.